Haven’t posted for a while as been very busy with work but let’s have a run through what’s been going on at this conversion.

So let’s have a look at the conversion in stages below we can see the existing boards removed and electrics being moved to make way for the new joists.

Loft striped out and electrics being moved
Loft striped out and electrics being moved

 

Here we can see the new beams going in for the new ashlar walls to sit on.

New beams going in for ashlar walls

Below we can see the new joists attached to the ring beam and the new ashlar wall sitting on top and floor being laid over

New ashlar walls and joists

 

Here we can see the access hatch and insulation going in

Insulation and access hatch going in

Here we can see multifoil installed over cleotex with batten on top and new vellum

Multifoil over cleotex with batten on top

Here we can see en-suite walls being built and velux installed

ensuite walls being built and velux installed

 

Here we can see the rear dormer being built

Rear dormer being built

Here we can see the dormer under construction and being clad with hard plank

Dormer under construction

Here we can see the internal walls and electrics going in

Internal walls and electrics going in

Thats all for the moment but will update this post with everything finished thanks for reading.

Haven’t posted for a while because been so busy with doing lofts this year so a quick post just to go though what’s been going on at CLC in 2021.

So we were commissioned to carry out a loft conversion at Defoe Rd this conversions was a big one with a flat dormer en-suite and some alterations to walls and making new openings downstairs.

The loft conversion also incorporated new cupboards in the sloping part of the roof and two large flying mullion windows and a pair of Keylite windows side by side.

So below we can see a few images of the loft at different stages of the build I will update these fully when the bathroom is complete next week.

We have all been carry out many garden rooms through our sister company CLS but will post on our other website and link back to this post.

Loft being fitted with multi foil and first fix electrics
Loft being fitted with multi foil and first fix electrics

 

Staris fitted with spindles and balustrades
Stairs fitted with spindles and balustrades

 

Roof watertight with three layer felt
Roof watertight with three layer felt

 

Loft plastered with side by side Keylite windows
Loft plastered with side by side Keylite windows

We can see the loft on construction at various stages of the build the build took around 3 months as there were walls to move downstairs and openings to cut out but as we can see the end result is outstanding if you would like a quote for a conversion like this don’t hesitate to contact us