Haven’t posted for a while as been very busy with work but let’s have a run through what’s been going on at this conversion.

So let’s have a look at the conversion in stages below we can see the existing boards removed and electrics being moved to make way for the new joists.

Loft striped out and electrics being moved
Loft striped out and electrics being moved

 

Here we can see the new beams going in for the new ashlar walls to sit on.

New beams going in for ashlar walls

Below we can see the new joists attached to the ring beam and the new ashlar wall sitting on top and floor being laid over

New ashlar walls and joists

 

Here we can see the access hatch and insulation going in

Insulation and access hatch going in

Here we can see multifoil installed over cleotex with batten on top and new vellum

Multifoil over cleotex with batten on top

Here we can see en-suite walls being built and velux installed

ensuite walls being built and velux installed

 

Here we can see the rear dormer being built

Rear dormer being built

Here we can see the dormer under construction and being clad with hard plank

Dormer under construction

Here we can see the internal walls and electrics going in

Internal walls and electrics going in

Thats all for the moment but will update this post with everything finished thanks for reading.