Well seeing as we are all stuck indoors for a while though I would post some picture of our most recent project below we can see work on a new extension stating the project is a timber framed extension with large slide and fold doors with a roof lantern.

Mini digger excavation for new foundations
Mini digger excavation for new foundations

We were commissioned to build a single story timber framed extension with massive slide and fold doors.

Shuttering ready for concrete
Shuttering ready for concrete pour

The shuttering you can see helps us keep the required width 450mm and the required depth 750mm and keeps a nice straight line and you might also spot the laser in the back ground this means the shuttering goes in level within 0.3mm tidy hey.

Concentre pored and shutters removed
Concentre pored and shutters removed

Here we can see the foundation with the shutters removed to show the correct width, depth and levelled in correctly.

Joist with vents
Joist with vents

Here we can see the first layer of blinding before the Dpm goes down we can also see the brick vents to provide ventilation for the floor

brick work with timber frame
Brick work with timber frame

Here we can see the brickwork installed and the timber frame sitting on the sole plate.

 

Joists installed
Joists installed

Here we can see the 9 inch brick wall backfilled with Dpm and a blinding of sand and cement onto of a 2000gsm membrane the joists sit in hangers with Dpm behind them so stop moisture ingress.

CLC have been carrying out many extensions and loft conversions though 2019, to much to put on the site so we will just focus on Wind-rush Rd where we were commissioned to carry out a loft conversions for a lovely couple. The conversion consisted of steel beams sitting on the outer walls to take the new joisted floor, ashlar walls and rest of the conversion.

 

Beams installed with ashlar walls
Beams installed with ashlar walls

Above we can see the joisting installed with ashlar walls with the insulation being placed within the floor we also had to install new 140mm rafters to take away the existing fink trusses.

 

Celotex installed
Celotex installed

Here we can see the celotex installed with lighting ring installed we can slo see the flue for the boiler which needs to be boxed in we can also see the velux installed.

Stairs being installed
Stairs being installed

Here we can see the installation of the stiar case which was particularly tight this is an open tread staircase we can also see the ashlar walls with structural ply installed.

Stairs installed
Stairs installed

Here we can see the stairs in the opening and the purlin to take the above rafters.

Landing being built
Landing being built

Here we can see the landing being built.

Open tread stairs installed
Open tread stairs installed

Here we can see the open tread stairs installed and protected

Loft plastered ready for painting
Loft plastered ready for painting

Here we can see the loft ready for plastering

Cupboards built to gain access to flue and storage
Cupboards built to gain access to flue and storage

Here we can see the cupboards built to gain access to the storage space and flue.